July 29, 2022

3201 Morganford - Q2 2022 Project Update

  Número de visitas:

0

Compartir:

The construction of 3201 Morganford has been slightly behind schedule (about 5 months), but the developers have made significant progress this quarter. Some highlights include:

  • The foundation work and elevator construction complete
  • The main staircase and structural steel framing.Storm retention has been completed
  • The staircase masonry shaft work is underway and continuing with one remaining shaft to be completed
  • The concrete footings work was completed at the end of JulyThe structural steel is fabricated and has been delivered to the site and has begun.
  • The structural steel is fabricated and has been delivered to the site and has begun.
  • The Y|O framing has begun to take shape.
  • The lumber is currently being fabricated and will be ready for delivery upon completion of the structural steel erection.
  • The tenant improvement package and plans are being finalized for our pre-lease commercial building.